You can review the status of upcoming and historical gates in the Projects page.
In this section:
The status of a gate's various policies is indicated by coloring segments of the gate's "donut" image. For example, the following gate indicates the status of 7 associated policies (4 unstable, 1 success, 1 failure, 1 no data):
Each policy's status is indicated as follows:
The overall gate status is calculated using the following process, and indicated with an icon in the middle of the gate's "donut" image.
If the build is in compliance with all policies, the gate status is set to Success and the following icon displays:
If any policy has an Error status, the build is out of compliance and the gate status is set to Error. This is marked with the following icon:
If the data for any policy is still being processed, the gate status is set to Refreshing. This is marked with a gray spinning circle icon in the middle of the donut:
If any policy has an Unstable status, the gate status is Unstable. This is marked with the following icon:
If none of the above conditions apply, the gate status is set to No Data. The No Data status applies to policies with the following conditions:
The No Data status is marked with the following icon:
To get a per-policy status breakdown, hover over the gate icon.
For additional details, see the policy information provided in the lower portion of the page.
By default, the gate details show the status of all associated policies. If you want to hide results for one or more policy status types, use the filter buttons at the top of the gate page.
To show previously-hidden policy types, just toggle the appropriate filter button.
For upcoming gates, the status icons indicate how well the project is satisfying the gate's policies. This helps you determine how much work is required to meet the expectations by the assigned date. You can navigate the timeline in different ways: