In addition to the AUTOSAR-specific widgets shipped with the artifact (see Viewing AUTOSAR Compliance Widgets), the dashboard includes three implementations of the native Categories - Top 5 Table DTP widget. The widgets are configured to use the AUTOSAR C++14 compliance categories shipped with the artifact.
...
- Compliant: Code meets all guidelines with no deviations or changes to the guideline categories.
- Not Compliant: Code does not meet all required guidelines.
- Missing rule(s) in analysis: Parasoft code analysis rules documented in your profile were not included in the specified build. Make sure all rules are enabled in the Parasoft tool and re-run the analysis.
- Compliant with Deviations: Code meets all guidelines, but deviations have been applied. Deviations are violations that you have determined to be acceptable (see Deviation Deviations Report for additional information about deviations).
- Compliant with Violations: Code meets all required guidelines but contains violations for advisory guidelines.
...
- Compliant: Code meets all guidelines with no deviations or changes to the guideline categories.
- Not Compliant: Code does not meet all required guidelines.
- Missing rule(s) in analysis: Parasoft code analysis rules documented in your profile were not included in the specified build. Make sure all rules are enabled in C/C++test the Parasoft tool and re-run the analysis.
- Compliant with Deviations: Code meets all guidelines, but deviations have been applied. Deviations are violations that you have determined to be acceptable (see Deviation Deviations Report for additional information about deviations).
- Compliant with Violations: Code meets all required guidelines but contains violations for advisory guidelines.
- No Rules Enabled: There are no Parasoft code analysis rules mapped to the guideline.
...
Table of Content Zone | ||||||
---|---|---|---|---|---|---|
| ||||||
Guideline Enforcement PlanThe Guidelines Enforcement Plan (GEP) lists the AUTOSAR guidelines mapped to Parasoft code analysis rules and other information to demonstrate how compliance is checked. This report uses the data specified in the compliance profile (see Custom Configuration of Profile). In the profile, you can add notes to the Compiler field, such as “no errors” or specific compiler settings that will be applied to document your plan. These notes appear in the Compiler column. The Analysis Tool column should refer to the static analysis rule. The Manual Review column should contain any manual verifications that will be performed in addition to the automated checks applied by the compiler and analysis tool. Guideline Re-categorization Plan Anchor |
You can change a guideline's obligation level from advisory to required and still claim compliance with AUTOSAR C++14. Guidelines cannot, however, be re-categorized as advisory. If you changed any of the AUTOSAR guideline categories (see Custom Configuration of Profile), they will be processed and displayed in this report. DeviationDeviations ReportA "deviation" is a documented violation of the guideline and supporting rationale for allowing the violation to remain. In the context of AUTOSAR compliance with Parasoft, deviations take the form of suppressed code analysis violations. Your project can have deviations and still be considered compliant if the deviations are documented in the report and do not impact safety. Your code can contain violations and still be AUTOSAR-compliant as long as the deviations from the standard are documented and that the safety of the software is unaffected. Deviations are code analysis rules that have been suppressed either directly in the code or in the DTP Violations Explorer. See the C++test documentation for details on suppressing violations in the code. See Prioritization Tab in the Violations Explorer documentation for information about suppressing violations in DTP. Click the Deviation Deviations Report link in the AUTOSAR Compliance report to open the Deviations Report. The Deviations Report shows all guideline IDs and headers, but guidelines that have been suppressed will show additional information. You can perform the following actions:
Build Audit ReportThe main AUTOSAR Compliance Report links to the Build Audit Report, which provides access to code analysis, test results, and coverage information sent to DTP under the selected build. This report also allows you to download an archive of the data, which is an artifact you can use to demonstrate compliance with AUTOSAR during a regulatory audit. The Build Audit Report is a standard report shipped with DTP and is not specific to AUTOSAR Compliance. In order to download an archive, the build has to be locked. See Build Audit Report for additional details about this report. |
...